Real-time production visibility on a legacy network
KPIs by machine and shift, calculated every hour with no manual work, from a communication network that is decades old.
The challenge
The plant ran on a legacy industrial network that could not integrate with modern platforms. Production reports were manual and scattered across daily spreadsheets. There was no history of efficiency, downtime or hourly production by machine type.
What we did
- 01 We integrated the existing network with custom-built PLC software, without replacing the field infrastructure.
- 02 We installed local displays with FactoryTalk Optix to show counters and variables on the plant floor.
- 03 We connected operations (OT) with information systems (IT) securely, using the existing corporate network.
- 04 In FactoryTalk DataMosaix we automated the hourly KPI calculation, with a shift view that reflects the actual operating schedule.
- 05 The project ran in four phases: survey, development, FAT/SAT testing and report automation.
Results
- 500 time series (machine counters) integrated into a single platform.
- Production, downtime and efficiency calculated automatically every hour, by machine and by shift.
- An auditable history of every hour of operation, accessible from anywhere.
- Operators log their observations and incidents in the same system, with permission control.
- FAT and SAT tests passed, without replacing field equipment.
/ Contact
Let's talk about your operation
The first step is an asset assessment. An engineer answers, not a form.
Our offices
- 66 West Flagler Street, 33130
United States
Ingedaca Inc.Local time
Get directions - Calle Heriberto Frías Ext. 1439, 03100
Mexico
Ingedaca S.A. de C.V.Local time
Get directions - La Trinidad, Calle Altagracia, Edificio Caracas Campus, Torre Wave, 1080
Venezuela
Ingedaca C.A.Local time
Get directions - Km 2 Vía Chía–Cajicá, costado occidental, Vereda Bojacá, Bizerta B1, Cundinamarca
Colombia
Ingedaca S.A.S.Local time
Get directions