05 Manufacturing

Preventive maintenance of electrical panels at a bottling plant

25 panels across 8 lines and the syrup room, serviced in 19 days without affecting production, each with its own report and recommendations.

The challenge

  • The electrical panels of several lines operated amid dust and vapors from sugary drinks.
  • Many had damaged latches, corrosion, overfilled cable ducts, conductors without terminals and blocked ventilation, all of which compromised their protection and reliability.
  • The work had to fit the plant’s scheduled shutdowns.

What we did

  1. 01
    On each panel we carried out inspection and diagnosis, re-tightened connections, organized the wiring, cleaned with dielectric solvents, restored ventilation and corrected faulty mountings.
  2. 02
    During the service we also diagnosed the cause of unexpected stoppages related to motion control.

Results

  • 25 panels serviced in 19 working days, coordinated with the plant’s scheduled shutdowns.
  • A service report for each panel, with specific recommendations.
  • The root cause of the stoppages was identified.
  • A recommendation plan for the plant: thermography under load, metalwork repair of corroded bases, grounding of doors, standardized labeling and implementation of a maintenance management system (CMMS).

/ Contact

Let's talk about your operation

The first step is an asset assessment. An engineer answers, not a form.

Email us info@ingedaca.com

Follow us

Our offices

United States Mexico Venezuela Colombia
Four offices, one team.
  1. United States

    Ingedaca Inc.
    66 West Flagler Street, 33130
    Get directions
  2. Mexico

    Ingedaca S.A. de C.V.
    Calle Heriberto Frías Ext. 1439, 03100
    Get directions
  3. Venezuela

    Ingedaca C.A.
    La Trinidad, Calle Altagracia, Edificio Caracas Campus, Torre Wave, 1080
    Get directions
  4. Colombia

    Ingedaca S.A.S.
    Km 2 Vía Chía–Cajicá, costado occidental, Vereda Bojacá, Bizerta B1, Cundinamarca
    Get directions